Hua Hin municipal officials visited Soi Chomsin 13 on March 17, 2025, to assess the progress of a reinforced concrete road construction project with a drainage system. The contractor has begun removing the existing concrete surface in sections of 30–40 meters per day, a process expected to take over a month. Following this, water supply infrastructure will be installed, and a new road with reinforced concrete and a V-shaped drainage channel will be built at the original elevation to prevent flooding in residential areas.

During the visit, Hua Hin Mayor Nopporn Wutthikul emphasized the importance of minimizing disruptions for local residents. He instructed the contractor to communicate with affected households about the construction process and ensure water supply reserves are arranged when installing the new system.